Before signature

The estimate that covered a third of what the client thought they were buying

Two documents described two different products and both carried our logo. I stopped the contract, wrote the discrepancy register, and split the release into a fundraising build and a regulated one.

How much of the client's version one the estimate actually covered
30–40%How much of the client's version one the estimate actually covered
Split into a fundraising build and a regulated build
2 milestonesSplit into a fundraising build and a regulated build
Document contradictions resolved before signature, not after
1 registerDocument contradictions resolved before signature, not after

The client

A venture-funded health-tech startup in Northern Europe, small in-house team, mid-fundraise. Building a clinical measurement product whose regulatory classification was still moving while the contract was being signed.

The engagement

Pre-contract scope alignment inside an active commercial negotiation — days, not weeks, with a signature date already in the calendar.

The problem

The client's idea of version one and our estimate were describing different products — ours covered roughly a third of theirs. While that was being reconciled the target moved again: the product was now heading toward registration as a regulated medical device, which pulls in a quality management system and a full clinical documentation package that no line of the estimate contained. On top of that, the commercial documents contradicted each other on the target platform and on the name of a core test.

What I did

I refused to let the contract close on ambiguity, which is the expensive kind of politeness. Every contradiction across the workbook, timeline, statement of work and invoice went into a single register with a proposed resolution and an owner, and the register went to the client rather than being quietly patched on our side. The milestone structure was renegotiated into two honestly different things: a front-end build whose job was to raise money, with the intelligence layer explicitly mocked, and a later regulated build carrying the device documentation. The regulatory package was flagged as new money rather than a variation, and a first-week feasibility spike on the hardware and integration path was made a precondition of committing to any date at all.

What was built

A scope reset delivered as three artefacts: a written gap analysis stating the delta as a percentage, a discrepancy register reconciling every contradiction across the commercial documents, and a re-cut milestone structure separating a front-end fundraising build from a later regulated build carrying the quality system and clinical documentation set.

On the table at the end

  • Gap analysis: our estimate against the client's stated version one
  • Discrepancy register across workbook, timeline, statement of work and invoice
  • Re-cut milestone structure with two definitions of done
  • Regulatory scope note identifying what the baseline never contained

What it changed

Prevented a contract from being signed on a scope gap of sixty to seventy per cent, converted an unfunded regulatory package into an explicit commercial decision rather than a later dispute, and gave the client a fundraising-ready milestone that did not depend on the regulated work landing first.

How it ran

  1. 01

    Name the gap in writing

    Our estimate against the client's version one, side by side, with the delta as a percentage rather than 'some differences'.

  2. 02

    Discrepancy register

    Every contradiction across the commercial documents listed with a proposed resolution and an owner, then walked through with the client rather than emailed.

  3. 03

    Re-cut the milestones

    A fundraising build with the intelligence mocked, and a later regulated build — two products with two definitions of done.

  4. 04

    Price the regulation

    Quality system, clinical document set and traceability matrix identified as absent from the baseline and raised as a separate commercial decision.

  5. 05

    Feasibility before commitment

    A first-week hardware and integration spike agreed as a gate, so the schedule rested on a tested assumption.

Something similar on your plate?

Thirty minutes, no deck. I will tell you whether it is worth doing at all.